Present construction documentation for review to Dept. of Parks and Recreation |
Barker Landscape Architects |
January |
 |
Final approval on 100% construction documents |
Steering Committee, Barker Landscape Architects |
February |
 |
Advertise and Issue bid documents |
Steering Committee, Barker Landscape Architects |
May |
 |
Fundraising 100% complete - Phase 1 |
Fundraising Team |
July |
 |
Award construction contract |
Steering Committee, Barker Landscape Architects |
August |
 |
Pre-construction meeting |
Steering Committee, Barker Landscape Architects |
August |
 |
Publicize, organize and schedule work parties |
Volunteer Coordinator, PR team |
September |
 |
Begin construction |
PJM Construction |
September |
 |
Conduct work parties to haul and spread wood chips and sand and install play equipment |
Volunteer Coordinator |
TBD |
 |
All site work completed |
|
TBD |
 |
Final punch list |
Steering Committee, Barker Landscape Architects |
TBD |
 |
Schedule and prepare for park opening |
Steering Committee |
TBD |
 |
Project complete |
|
TBD |
 |
Park Opening |
Steering Committee |
TBD |